[55951] in Hotline Meeting
Bldg. 66 -Subbasement (0040) Bldg. Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Aug 13 08:30:04 2001
Message-ID: <568F0AEE7A57D511923900508B556451155957@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'swetzel@mit.edu'" <swetzel@mit.edu>, "'jenns@mit.edu'"
<jenns@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 13 Aug 2001 08:24:30 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: swetzel@mit.edu; jenns@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 66 -Subbasement (0040) Bldg. Power Shutdown Request
>
>
The following building power shutdown request for Bldg. 66 - Subbasement
(0040) to feed Nuclear Magnetic Imaging Room on Wednesday, 8/15 is for your
review and comment. Would you please let me know whether this does or does
not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 66 - Subbsement (0040)
> Date: 8/15/2001
> Day: Wednesday
> Time: 7 AM - 3 PM
> System: Building Power
> Duration: 8 hours
> Reason:
> Relocate conduit for wall demolition.
>
> Effect:
> Loss of building power to 66 - 0040 Feed to Nuclear Magnetic Imaging Room
> only (Panel 4 - CI-26 next to 0051 Controls Panel NMR) during the 8-hour
> shutdown period..
>
>