[55931] in Hotline Meeting
Bldg. 56 - Emergency De-ionized Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 9 14:26:10 2001
Message-ID: <568F0AEE7A57D511923900508B55645115593F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'arolle@mit.edu'" <arolle@MIT.Edu>,
"'bengel@mit.edu'" <bengel@MIT.Edu>,
"'ccooney@mit.edu'"
<ccooney@MIT.Edu>,
"'cpoon@mit.edu'" <cpoon@MIT.Edu>, "'crg@mit.edu'"
<crg@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'dudley@mit.edu'"
<dudley@MIT.Edu>,
"'gibbhen@mit.edu'" <gibbhen@MIT.Edu>,
"'jmganno@mit.edu'" <jmganno@MIT.Edu>,
"'johnnyd@mit.edu'"
<johnnyd@MIT.Edu>, "'lsc@mit.edu'" <lsc@MIT.Edu>,
"'mbj@mit.edu'"
<mbj@MIT.Edu>,
"'mmahoney@mit.edu'" <mmahoney@MIT.Edu>,
"'nsteele@mit.edu'" <nsteele@MIT.Edu>,
"'patsys@mit.edu'"
<patsys@MIT.Edu>, "'rha@mit.edu'" <rha@MIT.Edu>,
"'rjwilk@mit.edu'"
<rjwilk@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'shyoung@mit.edu'" <shyoung@MIT.Edu>,
"'swetzel@mit.edu'"
<swetzel@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'cp-command@mit.edu'" <cp-command@MIT.Edu>,
"'mmahoney@mit.edu'"
<mmahoney@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>
Date: Thu, 9 Aug 2001 14:22:48 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; arolle@mit.edu; bengel@mit.edu; ccooney@mit.edu;
> cpoon@mit.edu; crg@mit.edu; Cust-Coach; dudley@mit.edu; gibbhen@mit.edu;
> jmganno@mit.edu; johnnyd@mit.edu; lsc@mit.edu; mbj@mit.edu;
> mmahoney@mit.edu; nsteele@mit.edu; patsys@mit.edu; rha@mit.edu;
> rjwilk@mit.edu; schedule@mit.edu; shyoung@mit.edu; swetzel@mit.edu;
> shutdowns@mit.edu; cp-command@mit.edu; mmahoney@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. 56 - Emergency De-ionized Shutdown
>
>
The following emergecy De-Ionized Water shutdown for Bldg. 56 for today,
Thursday, August 9 is for your information.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: 56
> Date: 8/9/2001
> Day: Thursday
> Time: 2:30 PM - 6 PM
> System: De-ioized Water
> Duration: 3 1/2 hours
> Reason:
> Glass drain pipe broke in Bldg. 16. Initially affected hot and cold lab
> process water in both Buildings 16 and then 56. Now de-ionized water in
> Bldg. 56 is also affected.
>
> Effect:
> Loss of de-ionized water in Bldg. 56 only.
>
>