[55911] in Hotline Meeting
Bldg. E52 - Air Handler Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 8 13:09:17 2001
Message-ID: <568F0AEE7A57D511923900508B55645115592A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.Edu>, "'gwj@mit.edu'" <gwj@MIT.Edu>,
"'lhill@mit.edu'" <lhill@MIT.Edu>,
"'lmorales@mit.edu'"
<lmorales@MIT.Edu>,
"'lreinher@mit.edu'" <lreinher@MIT.Edu>,
"'maureen@mit.edu'" <maureen@MIT.Edu>,
"'mscoppa@mit.edu'"
<mscoppa@MIT.Edu>, "'mwf@mit.edu'" <mwf@MIT.Edu>,
"'rberlin@mit.edu'"
<rberlin@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sdimond@mit.edu'" <sdimond@MIT.Edu>,
"'wganger@mit.edu'"
<wganger@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 8 Aug 2001 13:07:15 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: E-Zone; gwj@mit.edu; lhill@mit.edu; lmorales@mit.edu;
> lreinher@mit.edu; maureen@mit.edu; mscoppa@mit.edu; mwf@mit.edu;
> rberlin@mit.edu; schedule@mit.edu; sdimond@mit.edu; wganger@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E52 - Air Handler Shutdown Request
>
>
The following Air Handler system (supply ventilation, supply cooling and
exhaust-general air) shutdown request for Bldg. E52 on Friday, 8/24 PM to
Saturday, 8/25 PM is for your review and comment. Would you please let me
know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E52
> Date: 8/24/2001
> Day: Friday
> Time: 5 PM (8/24) - 5 PM (8/25)
> System: Air Handler/supply ventilation, supply cooling, exhaust-general
> air
> Duration: 24 hours
> Reason:
> Repair leaks in floor of Air Handler.
>
> Effect:
> Loss of supply ventilation, supply cooling and exhaust-general air in all
> of E52 during the shutdown period.
>
>