[55744] in Hotline Meeting
Bldg. NW21 - Rescheduled Compressed Lab Air Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 26 11:14:47 2001
Message-ID: <568F0AEE7A57D511923900508B556451155877@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'fulton@psfc.mit.edu'" <fulton@psfc.mit.edu>,
"'hrycaj@psfc.mit.edu'"
<hrycaj@psfc.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 26 Jul 2001 11:13:06 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: fulton@psfc.mit.edu; hrycaj@psfc.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. NW21 - Rescheduled Compressed Lab Air Shutdown Request
>
>
The following rescheduled compressed lab air shutdown request for Bldg. NW21
is now for Monday, 8/6. Would you please let me know if this new date has
your approval or does not.
Thank you again,
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: NW21
> Date: 8/6/2001
> Day: Monday
> Time: 8 AM - 11 AM
> System: Sullair Lab Air Compressor
> Duration: 3 hours
> Reason:
> Monthly maintenance.
>
> Effect:
> Loss of compressed lab air during the shutdown period.
>
>