[55741] in Hotline Meeting
Bldg. E17 - Critical Air Handler 1 and 2 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 26 08:46:46 2001
Message-ID: <568F0AEE7A57D511923900508B55645115586F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bengel@mit.edu'" <bengel@mit.edu>, E-Zone <E-Zone@mit.edu>,
"'jmganno@mit.edu'" <jmganno@mit.edu>,
"'lombardo@mit.edu'"
<lombardo@mit.edu>,
"'sdalton@mit.edu'" <sdalton@mit.edu>,
"'shyoung@mit.edu'" <shyoung@mit.edu>,
"'wardd@mit.edu'" <wardd@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 26 Jul 2001 08:45:04 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: bengel@mit.edu; E-Zone; jmganno@mit.edu; lombardo@mit.edu;
> sdalton@mit.edu; shyoung@mit.edu; wardd@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E17 - Critical Air Handler 1 and 2 Shutdown Request
>
>
The following Critical Air Handler 1 and 2 shutdown request for Bldg. E17 on
Thursday, 7/26 is for your information and comment. Would you please let me
know whether this does or does ot have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: E17
> Date: 7/26/2001
> Day: Thursday
> Time: 9 AM - 11 AM
> System: Air Handlers 1 and 2
> Duration: 2 hours
> Reason:
> To change belts on Air Handler 2 to improve static duct pressure.
>
> Effect:
> Some loss of supply cooling in E17 ( minimal effect on building cooling
> with cross-over open).
>
>