Bldg. 3 - Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 24 15:12:14 2001

Message-ID: <568F0AEE7A57D511923900508B556451155856@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'sdimond@mit.edu'" <sdimond@mit.edu>, "'mward@mit.edu'"
	 <mward@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 24 Jul 2001 15:10:35 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	sdimond@mit.edu; mward@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 3 - Chilled Water Shutdown Request
> 
> 
The following chilled water shutdown request for Bldg. 3 - 015, 011 and
Project Athena Room above on 1st floor on Tuesday, July 30 is for your
information and comment.  Would you please let me know whether this does or
does not have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 3 - 015 - 011 and  Project Athena Room above on 1st floor
> Date: 7/30/2001
> Day: Tuesday
> Time: 8 AM - 12 Noon
> System: Chilled Water
> Duration: 4 hours
> Reason: 
> Tie -in new fan coil units for 3-108.
> 
> Effect: 
> Loss of chilled water in 3 - 015 - 011 and Project Athena Room above on
> 1st floor during the shutdown period.
> 
> 