[55681] in Hotline Meeting
Bldg. 8 Building Power Revised Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 19 12:50:30 2001
Message-ID: <568F0AEE7A57D511923900508B556451155808@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'opsnote@mit.edu'" <opsnote@MIT.Edu>,
"'carolr@mit.edu'" <carolr@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'kmartel@mit.edu'"
<kmartel@MIT.Edu>,
"'lechtman@mit.edu'" <lechtman@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'ghughes@mit.edu'"
<ghughes@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'caross@mit.edu'" <caross@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
Steven Gilligan
<sgilliga@PLANT.MIT.EDU>,
"'geomac@mit.edu'" <geomac@MIT.Edu>, Doug Boyer <dboyer@PLANT.MIT.EDU>,
Eupremio Piccinonno
<Eupremio@PLANT.MIT.EDU>
Date: Thu, 19 Jul 2001 12:48:29 -0400
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Dear Everyone:
I have been informed the revised shutdown request for Bldg. 8 - Building
Power would now be for Tuesday, 7/24 at 6 PM to Wednesday, 7/25 to 6 AM.
Would you please let me know if these revised dates and times would have
your approval or not.
Thank you again for your time,
Andrea Nichols
Operations Center
8-7872