[55663] in Hotline Meeting
Bldg. 8 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 18 15:05:34 2001
Message-ID: <568F0AEE7A57D511923900508B5564511557EC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'opsnote@mit.edu'" <opsnote@MIT.Edu>,
"'carolr@mit.edu'" <carolr@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'kmartel@mit.edu'"
<kmartel@MIT.Edu>,
"'lechtman@mit.edu'" <lechtman@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'ghughes@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 18 Jul 2001 15:03:57 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; opsnote@mit.edu; carolr@mit.edu; Cust-Coach;
> glabonte@mit.edu; kmartel@mit.edu; lechtman@mit.edu; schedule@mit.edu;
> ghughes@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 8 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. 8 - 013T, 011, 035,
031, 032, 027, 016, 013, 10, 003, 004, 001 and 140 on Tuesday, 7/24 is for
your review and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 8 - 013T, 011, 035, 031, 032, 027, 016, 013, 10, 003, 004, 001
> and 140
> Date: 7/24/2001
> Day: Tuesday
> Time: 7 AM - 3 PM
> System: Building Power
> Duration: 8 hours
> Reason:
> Investigate, shutdown, install 2 new panel interiors (panels in 8-013E).
>
> Effect:
> Loss of building power in Telephone Room 013. Andover Communication - 011,
> Hot water circulating pump in 011. Will lose 208/120V power in all buildg.
> 8 basement rooms (035, 031, 032, 027, 016, 013, 10, 003, 004, 001. Will
> also lose power in 8-140 (SVT Shutter Analysis System) during the shutdown
> period.
>
>