[55648] in Hotline Meeting
Bldg. 68 - Air Handler 3 Critical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 17 14:26:33 2001
Message-ID: <568F0AEE7A57D511923900508B5564511557D1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'jfucillo@mit.edu'" <jfucillo@MIT.Edu>,
"'jmganno@mit.edu'"
<jmganno@MIT.Edu>,
"'maureen@mit.edu'" <maureen@MIT.Edu>,
"'rberlin@mit.edu'" <rberlin@MIT.Edu>,
"'shyoung@mit.edu'"
<shyoung@MIT.Edu>,
"'wganger@mit.edu'" <wganger@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 17 Jul 2001 14:25:02 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; jfucillo@mit.edu; jmganno@mit.edu;
> maureen@mit.edu; rberlin@mit.edu; shyoung@mit.edu; wganger@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 68 - Air Handler 3 Critical Shutdown Request
>
>
The following Critical shutdown request for Bldg. 68 - Air Handler 3/hood
make-up/supply air - (one-third supply and back-up for Air Handler 4 Animal
Quarters on Saturday, July 21 is for your review and comment. Would you
please let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 68 - all floors
> Date: 7/21/2001
> Day: Saturday
> Time: 7 AM - 3 PM
> System: Hood make-up/supply air for Air Handler 3
> Duration: 6 to 8 hours
> Reason:
> To repair cooling fans (3) for Variable Speed Drive (now operating at 50
> percent)
>
> Effect:
> Loss of supply ventilation, suplply cooling and supply heating in all of
> Bldg. 68 during the shutdown period.
>
>