Bldg. 39 - Supply Ventilation Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jul 16 11:48:54 2001

Message-ID: <568F0AEE7A57D511923900508B5564511557B1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'armay@mit.edu'" <armay@mit.edu>, B-Zone <B-Zone@mit.edu>,
        Cust-Coach
	 <cust-coach@mit.edu>, George Mac Leod <gmacleod@mit.edu>,
        "'mcgrath@mtl.mit.edu'" <mcgrath@mtl.mit.edu>,
        "'rcf@space.mit.edu'"
	 <rcf@space.mit.edu>,
        "'walsh@mtl.mit.edu'" <walsh@mtl.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 16 Jul 2001 11:47:25 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	armay@mit.edu; B-Zone; Cust-Coach; George Mac Leod;
> mcgrath@mtl.mit.edu; rcf@space.mit.edu; walsh@mtl.mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 39 - Supply Ventilation Shutdown Request
> 
> 
The following supply ventilation shutdown request for Bldg. 39 - 301 East
(Clean Rooms) on Friday, July 20 is for your review and comment.  Would you
please let me know whether this does or does not have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 39 - 301 East Clean Rooms
> Date: 7/20/2001
> Day: Friday
> Time: 7:30 AM - 11:30 AM
> System: Supply Ventilation
> Duration: 4 hours
> Reason: 
> Rewire Air Handler 1 (PM#708553) motor.
> 
> Effect: 
> Loss of supply ventilation in Blg. 39 - 301 East Clean Rooms during the
> shutdown period.
> 
> 