[55603] in Hotline Meeting
Bldg. E56 - Critical All Building Power Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 12 14:31:08 2001
Message-ID: <568F0AEE7A57D511923900508B55645115577E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'esimha@mit.edu'" <esimha@mit.edu>, "'gwj@mit.edu'" <gwj@mit.edu>,
"'lhill@mit.edu'" <lhill@mit.edu>,
"'mscoppa@mit.edu'" <mscoppa@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'mmahoney@mit.edu'" <mmahoney@mit.edu>,
"'safety@mit.edu'" <safety@mit.edu>,
"'cp-command@mit.edu'"
<cp-command@mit.edu>,
"'dempseyr@mit.edu'" <dempseyr@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Paul Stordy
<PStordy@PLANT.MIT.EDU>,
"'wpwohlfa@mit.edu'" <wpwohlfa@mit.edu>, E-Zone
<E-Zone@mit.edu>
Date: Thu, 12 Jul 2001 14:29:46 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: esimha@mit.edu; gwj@mit.edu; lhill@mit.edu; mscoppa@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu; mmahoney@mit.edu; safety@mit.edu;
> cp-command@mit.edu; dempseyr@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Paul Stordy;
> wpwohlfa@mit.edu; E-Zone
> Subject: Bldg. E56 - Critical All Building Power Shutdown
>
>
The following Critical All Building Power shutdown for Bldg. E56 on Friday,
7/13 is for your information. If you have any question about this, please
contact Paul Stordy at 8-9174.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: E56
> Date: 7/13/2001
> Day: Friday
> Time: 9 AM - 12 Noon
> System: All Building Power
> Duration: 3 hours
> Reason:
> NSTAR request (NSTAR Demand) transformer in imminent danger of exploding.
>
> Effect:
> Loss of power: access controls, emergency power, building power,
> elevators, computers, lighting - corridors, stairs; Air: supply
> ventilation, supply cooling, supply heating, exhaust-laboratory,
> exhaust-general and exhaust-toilet air during the 3-hour shutdown period.
>
>