Blg. 37 Emergency Air Handler 2/Chilled Water Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 12 10:57:49 2001

Message-ID: <568F0AEE7A57D511923900508B55645115577A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'alvarso@mit.edu'" <alvarso@mit.edu>, B-Zone <B-Zone@mit.edu>,
        "'benford@space.mit.edu'" <benford@space.mit.edu>,
        "'cmo@space.mit.edu'"
	 <cmo@space.mit.edu>,
        Cust-Coach <cust-coach@mit.edu>,
        "'droberts@mit.edu'" <droberts@mit.edu>,
        "'gallant@mit.edu'"
	 <gallant@mit.edu>,
        "'kane@mit.edu'" <kane@mit.edu>,
        "'murphy@space.mit.edu'" <murphy@space.mit.edu>,
        "'politano@mit.edu'"
	 <politano@mit.edu>,
        "'rcf@space.mit.edu'" <rcf@space.mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'wendell@mit.edu'"
	 <wendell@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'mmahoney@mit.edu'" <mmahoney@mit.edu>,
        Scott Brenner
	 <sbrenner@PLANT.MIT.EDU>, B-Zone <B-Zone@mit.edu>,
        "'cp-command@mit.edu'" <cp-command@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Thu, 12 Jul 2001 10:56:29 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	alvarso@mit.edu; B-Zone; benford@space.mit.edu; cmo@space.mit.edu;
> Cust-Coach; droberts@mit.edu; gallant@mit.edu; kane@mit.edu;
> murphy@space.mit.edu; politano@mit.edu; rcf@space.mit.edu;
> schedule@mit.edu; wendell@mit.edu; shutdowns@mit.edu; mmahoney@mit.edu;
> Scott Brenner; B-Zone; cp-command@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: 	Blg. 37 Emergency Air Handler 2/Chilled Water Shutdown
> 
> 
The following Emergency Air Handler 2/Chilled water shutdown for Bldg.
37-484 and rest of the building for today, Thursday, 7/1 is for your
information.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Emergency
> Building: 37 - 484 and rest of building
> Date: 7/12/2001
> Day: Thursday
> Time: 9:15 AM - 3:15 PM
> System: Air Handler 1/Chilled Water
> Duration: 8 hours or less
> Reason: 
> Loss of pressure in building causing Air Handler 2 and chilled water to
> fail. 
> 
> Effect: 
> Loss of Air Handler 2 (supply ventilation) to 37-474 and chilled water
> (air conditioning) to the rest of the building during the shutdown period.
> 
> 