Bldg. 13 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 11 08:27:17 2001
Message-ID: <568F0AEE7A57D511923900508B556451155758@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'elk@mit.edu'" <elk@MIT.Edu>, "'schedule@mit.edu'" <schedule@MIT.Edu>,
"'src@mit.edu'" <src@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 11 Jul 2001 08:25:58 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; elk@mit.edu; schedule@mit.edu; src@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 13 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 13 - 5095, 5099,
5119, 5101, 5127, 5143 and 5147 on Monday, July 16 thru Friday, July 20 is
for your review and comment. Would you please let me know whether this does
or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 13 - 5095, 5099, 5119, 5101, 5127, 5143 and 5147
> Date: 7/16/2001
> Day: Monday
> Time: 6 AM (7/16) - 2 PM (7/20)
> System: Chilled Water (air conditioning)
> Duration: 5 days (120 hours))
> Reason:
> To relocate valves and piping for new duct path.
>
> Effect:
> Loss of chilled water to fan coil units (air conditioning only) in 13 -
> 5095, 5099, 5119, 5101, 5127, 5143 and 5147 during the shutdown period.
>
>