Shutdown request for building 37 on 7/6/01
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Jul 3 08:19:26 2001
Message-ID: <568F0AEE7A57D511923900508B5564513F4C58@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: alvarso@mit.edu, B-Zone <B-Zone@mit.edu>, benford@space.mit.edu,
cmo@space.mit.edu, Cust-Coach <cust-coach@mit.edu>, gallant@mit.edu,
kane@mit.edu, murphy@space.mit.edu, politano@mit.edu,
rcf@space.mit.edu, schedule@mit.edu, wendell@mit.edu,
shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 3 Jul 2001 08:18:16 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: alvarso@mit.edu; B-Zone; benford@space.mit.edu; cmo@space.mit.edu;
> Cust-Coach; gallant@mit.edu; kane@mit.edu; murphy@space.mit.edu;
> politano@mit.edu; rcf@space.mit.edu; schedule@mit.edu; wendell@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 37 on 7/6/01
>
>
The following shutdown request is for building 37 on 7/6/01. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 37
> Date: 7/6/01
> Day: Friday
> Time: 8 am - 2 pm
> System: Fire protection water
> Duration: 6 hours
> Reason:
> To isolate the east end penthouse to make way for a skylight and install
> zone control.
>
> Effect:
> The fire protection water will be down during this time.
>
>