[55485] in Hotline Meeting
Bldg. 13 Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 28 09:16:18 2001
Message-ID: <568F0AEE7A57D511923900508B556451155719@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'elk@mit.edu'" <elk@MIT.Edu>, "'schedule@mit.edu'" <schedule@MIT.Edu>,
"'src@mit.edu'" <src@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 28 Jun 2001 09:15:12 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; elk@mit.edu; schedule@mit.edu; src@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 13 Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 13 - 5095, 5099,
5119, 5101, 5127, 5143 and 5147 on Monday, July 2, Tuesday, July 3,
Wednesday, July 4 (equipment off only), Thursday, July 5 and Friday, July 6
is for your review and comment. Would you please let me know whether this
does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 13 - 5095, 5099, 5119, 5101, 5127, 5143 and 5147
> Date: 7/2/2001
> Day: Monday
> Time: 6 AM (7/2) - 2 PM (7/6)
> System: Fan Coil (chilled water) - air conditioning
> Duration: 5 days (120 hours)
> Reason:
> To relocate piping and valves for new duct path.
>
> Effect:
> Loss of chilled water (air conditioning) in the above listed rooms only
> during the shutdown period.
>
>