Bldg. 35 Rescheduled Domestic Hot and Cold Water Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 26 09:32:06 2001
Message-ID: <568F0AEE7A57D511923900508B5564511556F5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'gerwent@mit.edu'"
<gerwent@MIT.Edu>,
"'inslee@mit.edu'" <inslee@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'stiffler@mit.edu'"
<stiffler@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Vinny Clark
<VClark@PLANT.MIT.EDU>
Date: Tue, 26 Jun 2001 09:31:10 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; gallant@mit.edu; gerwent@mit.edu;
> inslee@mit.edu; schedule@mit.edu; stiffler@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Vinny Clark
> Subject: Bldg. 35 Rescheduled Domestic Hot and Cold Water Shutdown
>
>
Dear Everyone:
It has been requested the shutdown for Bldg. 35 initially for Thursday,
6/28 be rescheduled to Friday, July 6. Would you please let me know if this
new date has your approval or does not.
Thank you again for your time,
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 35
> Date: 7/6/2001
> Day: Friday
> Time: 6 AM - 2 PM
> System: Domestic Hot and Cold Water
> Duration: 8 hours
> Reason:
> Install new ball valves.
>
> Effect:
> Loss of domestic hot and cold water. This means there will be no water for
> toilets, bathroom, kitchen sink faucets or drinking fountains during the
> shutdown period.
>
>