Bldgs. 6 and 18 - Hot and Cold Domestic and Lab Process Water Shu

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 25 12:35:21 2001

Message-ID: <568F0AEE7A57D511923900508B5564511556ED@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rjwilk@mit.edu'" <rjwilk@mit.edu>, "'mbj@mit.edu'" <mbj@mit.edu>,
        "'crg@mit.edu'" <crg@mit.edu>, "'msfeld@mit.edu'" <msfeld@mit.edu>,
        C-Zone <C-Zone@mit.edu>, "'ctmunger@mit.edu'" <ctmunger@mit.edu>,
        Cust-Coach <cust-coach@mit.edu>,
        "'cwyckoff@mit.edu'" <cwyckoff@mit.edu>,
        "'glabonte@mit.edu'" <glabonte@mit.edu>,
        "'khewitt@mit.edu'"
	 <khewitt@mit.edu>,
        "'mhankin@mit.edu'" <mhankin@mit.edu>,
        "'rhasselt@MIT.EDU'" <rhasselt@mit.edu>,
        "'rrdasari@mit.edu'"
	 <rrdasari@mit.edu>,
        "'saraf@mit.edu'" <saraf@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'vesau@mit.edu'"
	 <vesau@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 25 Jun 2001 12:34:19 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	rjwilk@mit.edu; mbj@mit.edu; crg@mit.edu; msfeld@mit.edu; C-Zone;
> ctmunger@mit.edu; Cust-Coach; cwyckoff@mit.edu; glabonte@mit.edu;
> khewitt@mit.edu; mhankin@mit.edu; rhasselt@MIT.EDU; rrdasari@mit.edu;
> saraf@mit.edu; schedule@mit.edu; vesau@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. 6 and 18 - Hot and Cold Domestic and Lab Process
> Water Shutdown Request
> 
> 
The following hot and cold domestic and lab process water shutdown request
for Bldgs. 6 and 18 on Thursday, 6/28 is for your review and comment.  Would
you please let me know whether this does or does not have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 6 and 18
> Date: 6/28/2001
> Day: Thursday
> Time: 7 PM - 12 midnight
> System: All hot and cold domestic and lab process water
> Duration: 5 hours
> Reason: 
> Shutdown water flow so acid waste sump in Bldg 18 can be pumped down and
> inspected.
> 
> Effect: 
> Loss of all hot and cold domestic (affects toilets, bathroom, kitchen, lab
> sink faucets and drinking fountains) and hot and cold lab process water
> (affects lab equipment requiring use of same -- lasers. etc. and lab
> sinks) during the 4-hour shutdown period.
> 
> 