[55359] in Hotline Meeting
Bldgs. 3 and 1 Compressed Lab Air Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 14 08:35:13 2001
Message-ID: <568F0AEE7A57D511923900508B556451155652@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'arhodes@mit.edu'" <arhodes@mit.edu>, C-Zone <C-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
"'dfucillo@mit.edu'" <dfucillo@mit.edu>,
"'dory@mit.edu'" <dory@mit.edu>,
"'engler@mitvma.mit.edu'" <engler@mitvma.mit.edu>,
"'fenner@mit.edu'"
<fenner@mit.edu>,
"'gossard@mit.edu'" <gossard@mit.edu>,
"'honda@mit.edu'" <honda@mit.edu>, "'ikec@mit.edu'" <ikec@mit.edu>,
"'jobrien@mit.edu'" <jobrien@mit.edu>,
"'lsandler@mit.edu'"
<lsandler@mit.edu>,
"'mamullow@mit.edu'" <mamullow@mit.edu>, "'ndk@mit.edu'" <ndk@mit.edu>,
"'placido@mit.edu'" <placido@mit.edu>,
"'psking@mit.edu'" <psking@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'sdimond@mit.edu'" <sdimond@mit.edu>,
"'sexton@mit.edu'" <sexton@mit.edu>,
"'tetaylor@mit.edu'"
<tetaylor@mit.edu>,
"'vipinternal@mit.edu'" <vipinternal@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 14 Jun 2001 08:34:32 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: arhodes@mit.edu; C-Zone; Cust-Coach; Cust-Coach; dfucillo@mit.edu;
> dory@mit.edu; engler@mitvma.mit.edu; fenner@mit.edu; gossard@mit.edu;
> honda@mit.edu; ikec@mit.edu; jobrien@mit.edu; lsandler@mit.edu;
> mamullow@mit.edu; ndk@mit.edu; placido@mit.edu; psking@mit.edu;
> schedule@mit.edu; sdimond@mit.edu; sexton@mit.edu; tetaylor@mit.edu;
> vipinternal@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 3 and 1 Compressed Lab Air Shutdown Request
>
>
The following compressed lab air shutdown request for Bldgs. 3 (all labs)
and Bldg. 1 - d'Arbeloff Lab only on Wednesday, 6/20 is for your information
and comment. Would you please let me know whether this does or does not
have your approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 3 - all labs and 1 (d-Arbeloff Lab only)
> Date: 6/20/2001
> Day: Wednesday
> Time: 6:30 AM - 7:30 AM
> System: Compressed Lab Air
> Duration: 1 hour
> Reason:
> Tie into lab air main for service to 3-370.
>
> Effect:
> Loss of compressed lab air in Bldg. 3 (all labs) and Bldg. 1 (d'Arbeloff
> Lab only) during the 1-hour shutdown period.
>
>