Bldg. 1 - 206, 214 Approved Fire Alarm Shutdown - Revised
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 11 13:41:50 2001
Message-ID: <568F0AEE7A57D511923900508B556451155625@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'dfucillo@mit.edu'" <dfucillo@MIT.Edu>,
"'fenner@mit.edu'"
<fenner@MIT.Edu>,
"'jellyfin@mit.edu'" <jellyfin@MIT.Edu>,
"'magowen@mit.edu'" <magowen@MIT.Edu>,
"'mamullow@mit.edu'"
<mamullow@MIT.Edu>,
"'mgibson@mit.edu'" <mgibson@MIT.Edu>,
"'patdixon@mit.edu'" <patdixon@MIT.Edu>,
"'rlbras@mit.edu'"
<rlbras@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'scottc@mit.edu'" <scottc@MIT.Edu>,
"'skanode@mit.edu'"
<skanode@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
Howard Harrison <HHarriso@PLANT.MIT.EDU>,
"'rcatella@mit.edu'"
<rcatella@MIT.Edu>,
"'safety@mit.edu'" <safety@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>
Date: Mon, 11 Jun 2001 13:41:14 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; Cust-Coach; dfucillo@mit.edu; fenner@mit.edu;
> jellyfin@mit.edu; magowen@mit.edu; mamullow@mit.edu; mgibson@mit.edu;
> patdixon@mit.edu; rlbras@mit.edu; schedule@mit.edu; scottc@mit.edu;
> skanode@mit.edu; shutdowns@mit.edu; Howard Harrison; rcatella@mit.edu;
> safety@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer
> Subject: Bldg. 1 - 206, 214 Approved Fire Alarm Shutdown - Revised
>
>
The following approved fire alarm shutdown for Bldg 1 - 206, 214 and the
rest of the building on Thursday, 6/14 is for your information. If you have
any question about this, please contact Mr. Ronald Catella at 8-6811.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 1 - 206, 214 and rest of the building
> Date: 6/14/2001
> Day: Thursday
> Time: 10 AM - 11 AM
> System: Fire Alarm
> Duration: 1 hour
> Reason:
> Cambrige Fire Department walkthru, testing of horns and strobes.
> Cambridge Fire Depratment walkthru, testing of horns and strobes.
>
> Effect:
> Loss of fire alarm system in Bldg. 1 during the 1-hour shutdown/testing.
> There will be live audible testing of the building fire alarm system. All
> alarms heard before and after this time period should be considered actual
> alarms and occupants should follow the building evacuation plan.
>
>