Bldg. 39 - Compressed Lab Air Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 7 08:51:42 2001

Message-ID: <568F0AEE7A57D511923900508B5564511555E1@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'armay@mit.edu'" <armay@mit.edu>, B-Zone <B-Zone@mit.edu>,
        Cust-Coach
	 <cust-coach@mit.edu>, George Mac Leod <gmacleod@mit.edu>,
        "'mcgrath@mtl.mit.edu'" <mcgrath@mtl.mit.edu>,
        "'rcf@space.mit.edu'"
	 <rcf@space.mit.edu>,
        "'walsh@mtl.mit.edu'" <walsh@mtl.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 7 Jun 2001 08:51:10 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	armay@mit.edu; B-Zone; Cust-Coach; George Mac Leod;
> mcgrath@mtl.mit.edu; rcf@space.mit.edu; walsh@mtl.mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 39 - Compressed Lab Air Shutdown Request
> 
> 
The following compressed lab air shutdown request for Bldg. 39 on Monday,
June 18 through Monday, June 25 is for your review and comment.  Would you
please let me know whether this does or does not have your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 39
> Date: 6/18/2001
> Day: Monday
> Time: 7 AM (6/18) - 3 PM (6/25)
> System: Compressed Lab Air
> Duration: 8 days
> Reason: 
> Installation of new compressors.
> 
> Effect: 
> Loss of compressed lab air in Bldg. 39 during the shutdown period.
> 
> 