[55241] in Hotline Meeting
Bldg. 9 - Floor 2, 3 and 4 Critical Asbestos Removal/Shutdown Not
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 4 14:41:43 2001
Message-ID: <568F0AEE7A57D511923900508B5564511555AE@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'deedc@mit.edu'" <deedc@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'jobrien@mit.edu'" <jobrien@MIT.Edu>,
"'kirky@ceci.mit.edu'"
<kirky@ceci.mit.edu>,
"'mlavalle@mitvma.mit.edu'"
<mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'" <ndk@MIT.Edu>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
"'randy@mit.edu'"
<randy@MIT.Edu>,
"'sexton@mit.edu'" <sexton@MIT.Edu>, "'src@mit.edu'"
<src@MIT.Edu>,
"'westlund@mit.edu'" <westlund@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'lordjim@mit.edu'"
<lordjim@MIT.Edu>,
"'mmahoney@mit.edu'" <mmahoney@MIT.Edu>, "'tr6@mit.edu'" <tr6@MIT.Edu>,
"'jdoucett@mit.edu'" <jdoucett@MIT.Edu>,
"'tdoyle@mit.edu'" <tdoyle@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>, C-Zone <C-Zone@MIT.Edu>,
"'geomac@mit.edu'" <geomac@MIT.Edu>
Date: Mon, 4 Jun 2001 14:41:08 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; Cust-Coach; deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> kirky@ceci.mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu;
> pam@ceci.mit.edu; randy@mit.edu; sexton@mit.edu; src@mit.edu;
> westlund@mit.edu; shutdowns@mit.edu; lordjim@mit.edu; mmahoney@mit.edu;
> tr6@mit.edu; jdoucett@mit.edu; tdoyle@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; C-Zone; geomac@mit.edu
> Subject: Bldg. 9 - Floor 2, 3 and 4 Critical Asbestos
> Removal/Shutdown Notification
>
>
The following Critical asbestos removal/shtudown notification for Bldg. 9 -
floors 2, 3 and 4 on Monday, 6/4 through Monday, 6/11 is for your
information. If you have any question about this, please contact George
MacDonald at 3-0831.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 9 - floors 2, 3 and 4
> Date: 6/4/2001
> Day: Monday
> Time: 7:30 AM (6/4) - 3 PM (6/11)
> System: Air Handler 1 (supply ventilation), REturn Fan 1 (Return Air)
> Duration: 1 week
> Reason:
> Asbestos abatement on 5th floor tiles.
>
> Effect:
> Loss of supply ventilation in Bldg. 9 - floors 2, 3 and 4 as well as
> return air. * Air Handler 1/Supply Fan 1 will be set for 100 percent
> outside air.
>
>