[55181] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 66 - Air Handler 3 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri May 25 09:53:05 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD2542@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'ccooney@mit.edu'" <ccooney@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'patsys@mit.edu'" <patsys@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'swetzel@mit.edu'"
	 <swetzel@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 25 May 2001 09:52:52 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; ccooney@mit.edu; Cust-Coach; patsys@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 66 - Air Handler 3 Shutdown Request
> 
> 
The following shutdown request for Bldg. 66 - Interior Zone (Air Handler 3)
on Thursday, 5/31 is for your information and comment.  Would you please let
me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 66 - Interior Zone
> Date: 5/31/2001
> Day: Thursday
> Time: 3 PM - 7 PM
> System: Air Handler 3 (supply ventilation)
> Duration: 4 hours
> Reason: 
> Repair and find chill water leak.
> 
> Effect: 
> Loss of Air Handler 3 (PM#702541) -supply ventilation- during the 4-hour
> shutdown period.
> 
> 

home help back first fref pref prev next nref lref last post