Bldg. 66 Supply Ventilation Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 15 13:53:38 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD246E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'ccooney@mit.edu'" <ccooney@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'patsys@mit.edu'" <patsys@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'swetzel@mit.edu'"
	 <swetzel@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 15 May 2001 13:53:30 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; ccooney@mit.edu; Cust-Coach; patsys@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 66 Supply Ventilation Shutdown Request
> 
> 
The following supply ventilation shutdown request for Bldg. 66 - Floors 1 -
5 on Monday, 5/21 is for your information and comment.  Would you please let
me know whether this does or does not meet with your approval.

Thank you,

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 66
> Date: 5/21/2001
> Day: Monday
> Time: 7 AM - 12 Noon
> System: Air Handler 1-Return Fan 2 (PM#702534)
> Duration: 4 hours
> Reason: 
> Annual Preventive Maintenance work.
> 
> Effect: 
> Loss of supply ventilation (air from outside) in Bldg. 66 - floors 1
> through 5 during the 4-hour shutdown period.
> 
> 