[55039] in Hotline Meeting
Bldg. 68 - Supply Cooling/Supply Heating Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 15 11:13:41 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2466@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'jfucillo@mit.edu'" <jfucillo@MIT.Edu>,
"'jmganno@mit.edu'"
<jmganno@MIT.Edu>,
"'maureen@mit.edu'" <maureen@MIT.Edu>,
"'rberlin@mit.edu'" <rberlin@MIT.Edu>,
"'shyoung@mit.edu'"
<shyoung@MIT.Edu>,
"'wganger@mit.edu'" <wganger@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'wplynch@mit.edu'"
<wplynch@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 15 May 2001 11:13:35 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; jfucillo@mit.edu; jmganno@mit.edu;
> maureen@mit.edu; rberlin@mit.edu; shyoung@mit.edu; wganger@mit.edu;
> shutdowns@mit.edu; wplynch@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 68 - Supply Cooling/Supply Heating Shutdown Request
>
>
The following supply cooling/supply heating shutdown request for Bldg. 68 on
Monday, 5/21 is for your review and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 68
> Date: 5/21/2001
> Day: Monday
> Time: 12 noon - 3 PM
> System: Fan Supply/Air Handler 1A and B
> Duration: 3 hours
> Reason:
> Annual preventive maintenance work on PM#715496. This is Fan Supply Air
> Handler A1 and B.
>
> Effect:
> Loss of supply cooling/supply heating in Bldg. 68 via PM#715496 (Fan
> Supply Air Handler 1A and B during the 3-hour shutdown period.
>
>