[54982] in Hotline Meeting
Bldg. E32 - Chilled Water Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri May 11 12:41:34 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2434@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.Edu>, "'mshenry@mit.edu'" <mshenry@MIT.Edu>,
"'mwhelan@mit.edu'" <mwhelan@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>,
"'kcn@mit.edu'" <kcn@MIT.Edu>, "'gscot@mit.edu'"
<gscot@MIT.Edu>,
"'jmcd@mit.edu'" <jmcd@MIT.Edu>, "'cbates@mit.edu'"
<cbates@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 11 May 2001 12:41:29 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: E-Zone; mshenry@mit.edu; mwhelan@mit.edu; shutdowns@mit.edu;
> kcn@mit.edu; gscot@mit.edu; jmcd@mit.edu; cbates@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E32 - Chilled Water Shutdown
>
>
The following chilled water shutdown for Bldg. E32 on Monday, 5/14 is for
your information and comment. Would you please let me know whether this
does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: E32
> Date: 5/14/2001
> Day: Monday
> Time: 7 AM - 3 PM
> System: Chilled Water
> Duration: 8 hours
> Reason:
> Removal of air conditioning units in rooms 128 and 305 Conference Rooms.
>
> Effect:
> Loss of air conditioning in E32 during the shutdown period.
>
>