[54875] in Hotline Meeting
Bldg. 26 - 044, 152, 244, 248, 348, 448 and 548 - 5/5 - Approved
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 3 08:52:50 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2390@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Kevin Carpenter <kjcarpen@PLANT.MIT.EDU>,
"'mmahoney@mit.edu'"
<mmahoney@mit.edu>,
Steven Gilligan <sgilliga@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>, B-Zone <B-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Date: Thu, 3 May 2001 08:52:45 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: Kevin Carpenter; mmahoney@mit.edu; Steven Gilligan
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; B-Zone; Cust-Coach;
> shutdowns@mit.edu
> Subject: Bldg. 26 - 044, 152, 244, 248, 348, 448 and 548 - 5/5 -
> Approved Building Power Lighting, HVAC Shutdown
>
>
The following approved shutdown for Bldg. 26 - 044, 152, 244, 248, 348, 448
and 548 on Saturday, 5/5 is for your information.
Thank you.
Andrea Nichols
Operataions Center
8-7872
> Status: Normal
> Building: 26 - 044, 152, 244, 248, 348, 448 and 548
> Date: 5/5/2001
> Day: Saturday
> Time: 7 AM - 3 PM
> System: Building power, lighting, HVAC
> Duration: 8 hours
> Reason:
> Electrical panel retrofit.
>
> Effect:
> Loss of Power: Building power, computers, lighting; Air: supply
> ventilation, supply cooling, supply heating, exhaust-laboratory,
> exhaust-general, compressed lab and lab vacuum air; Other: Exhaust Hood
> during the 8-hour shutdown period.
>
>