[54858] in Hotline Meeting
Bldg. 9 - 235, 253, 250, 251, 313, 317, 321, 323, 325, 327, 329,
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed May 2 09:44:27 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2372@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'deedc@mit.edu'" <deedc@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'jobrien@mit.edu'" <jobrien@MIT.Edu>,
"'kirky@ceci.mit.edu'"
<kirky@ceci.mit.edu>,
"'mlavalle@mitvma.mit.edu'"
<mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'" <ndk@MIT.Edu>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
"'randy@mit.edu'"
<randy@MIT.Edu>,
"'sexton@mit.edu'" <sexton@MIT.Edu>, "'src@mit.edu'"
<src@MIT.Edu>,
"'westlund@mit.edu'" <westlund@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 2 May 2001 09:44:13 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; Cust-Coach; deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> kirky@ceci.mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu;
> pam@ceci.mit.edu; randy@mit.edu; sexton@mit.edu; src@mit.edu;
> westlund@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 9 - 235, 253, 250, 251, 313, 317, 321, 323, 325, 327,
> 329, 335, 355, 427, 449, 550, 551 and 552 - 5/8 Revised Chilled Water
> Shutdown Request
>
>
The following revised chilled water shutdown request for Bldg. 9 - 235, 253,
250, 251, 313, 317, 321, 323, 325, 327, 329, 335, 355, 427, 449, 550, 551
and 552 on Tuesday, May 8 is again for your review and comment. Would you
please let me know whether this does or does not meet with your approval.
Thank you,
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 9 - 235, 253, 250, 251, 313, 317, 321, 323, 325, 327, 329, 335,
> 355, 427, 449, 550, 551 and 552
> Date: 5/8/2001
> Day: Tuesday
> Time: 7:30 AM - 2:30 PM
> System: Chilled Water
> Duration: 7 hours
> Reason:
> Tie in new fan coil units.
>
> Effect:
> Loss of chilled water (air conditioning) to the rooms listed above during
> the shutdown period.
>
>