[54716] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. W8 - Boathouse - 4/20 Approved Critical All Normal Power Sh

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Apr 19 13:15:06 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD22A5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Paul Stordy <PStordy@PLANT.MIT.EDU>,
        James Sullivan
	 <jsulliva@PLANT.MIT.EDU>,
        "'mmoreira@plant.mit.edu'"
	 <mmoreira@PLANT.MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        D-Zone
	 <D-Zone@mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'djmartin@mit.edu'"
	 <djmartin@mit.edu>,
        "'slett@mit.edu'" <slett@mit.edu>
Date: Thu, 19 Apr 2001 13:14:48 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	Paul Stordy; James Sullivan; mmoreira@plant.mit.edu;
> mmahoney@mit.edu
> Cc: 	shutdown@plant.mit.edu; D-Zone; rm-shutdown@mit.edu;
> shutdowns@mit.edu; djmartin@mit.edu; slett@mit.edu
> Subject: 	Bldg. W8 - Boathouse - 4/20 Approved Critical All Normal
> Power Shutdown
> 
> 
The following approved all normal power shutdown for Bldg. W8 (Boathouse) on
Friday, 4/20 is for your information.

Thank you,

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: W8 (Boathouse)
> Date: 4/20/01
> Day: Friday
> Time: 10 AM - 10:30 AM
> System: All normal Power
> Duration: 30 minutes
> Reason: 
> Acquire correct phasing for W4.
> 
> Effect: 
> Loss of Power: access controls, building power, computers, lighting -
> corridors/stairs during the 30 minute shutdown period.
> 
> 