Bldg. W8 - 4/20 Critical All Normal Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Apr 19 08:44:02 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD229A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'djmartin@mit.edu'" <djmartin@mit.edu>,
        "'slett@mit.edu'"
	 <slett@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 19 Apr 2001 08:43:52 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	djmartin@mit.edu; slett@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. W8 - 4/20 Critical All Normal Power Shutdown Request
> 
> 
The following Critical All Normal Power shutdown for Bldg. W8 on Friday,
4/20 is for your information.  Would you please let me know whether this
does or does not meet with your approval.

Thank you,

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: W8
> Date: 4/20/2001
> Day: Friday
> Time: unknown
> System: All Normal Power
> Duration: 1 hour (really 20 minutes)
> Reason: 
> Acquire correct phasing for W4.
> 
> Effect: 
> Loss of Power: access controls, building power, computers, lighting -
> corridors/stairs during the shutdown period.
> 
> 