[54688] in Hotline Meeting
Bldgs. W89, W11 and W45 - 4/21 - All Electrical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Apr 18 08:55:10 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2289@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'carleton@mit.edu'" <carleton@mit.edu>, D-Zone <D-Zone@mit.edu>,
"'klhewitt@mit.edu'" <klhewitt@mit.edu>, "'let@mit.edu'" <let@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'mwf@mit.edu'" <mwf@mit.edu>, "'pwalsh@mit.edu'" <pwalsh@mit.edu>,
"'rberlin@mit.edu'"
<rberlin@mit.edu>,
"'sbenj@mit.edu'" <sbenj@mit.edu>,
"'wganger@mit.edu'" <wganger@mit.edu>,
"'nmagnuso@mit.edu'"
<nmagnuso@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 18 Apr 2001 08:55:01 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: carleton@mit.edu; D-Zone; klhewitt@mit.edu; let@mit.edu;
> shutdowns@mit.edu; mwf@mit.edu; pwalsh@mit.edu; rberlin@mit.edu;
> sbenj@mit.edu; wganger@mit.edu; nmagnuso@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. W89, W11 and W45 - 4/21 - All Electrical Shutdown
> Request
>
>
The following all electrical shutdown request for Bldgs. W89, W11 and W45 on
Saturday, 4/21 is for your information. Would you please let me know
whether this does or does not have your approval.
Thank you,
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: W89, W11 and W45
> Date: 4/21/2001
> Day: Saturday
> Time: 5 AM - 5:05 AM
> System: All Electrical Power
> Duration: 5 minutes
> Reason:
> NSTAR request.
>
> Effect:
> Loss of Power: access controls, building power, computers, lighting -