[54667] in Hotline Meeting

home help back first fref pref prev next nref lref last post

No subject found in mail header

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Apr 17 15:04:22 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD227E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'fredmcw@mit.edu'" <fredmcw@mit.edu>,
        "'hallisey@mit.edu'"
	 <hallisey@mit.edu>,
        "'jbernard@mit.edu'" <jbernard@mit.edu>,
        "'opsnote@mit.edu'" <opsnote@mit.edu>,
        "'shutdown@mit.edu'"
	 <shutdown@mit.edu>,
        "'actinide@mit.edu'" <actinide@mit.edu>, D-Zone
	 <D-Zone@mit.edu>,
        "'eslau@mit.edu'" <eslau@mit.edu>,
        "'fafrey@mit.edu'"
	 <fafrey@mit.edu>,
        "'fredmcw@mit.edu'" <fredmcw@mit.edu>,
        "'ginipig@MIT.EDU'" <ginipig@mit.edu>,
        "'ila@bhoomi.mit.edu'"
	 <ila@bhoomi.mit.edu>,
        "'jbernard@mit.edu'" <jbernard@mit.edu>,
        "'kczer@MIT.EDU'" <kczer@mit.edu>,
        "'klnoyes@MIT.EDU'" <klnoyes@mit.edu>,
        "'politano@mit.edu'" <politano@mit.edu>,
        "'safety@mit.edu'"
	 <safety@mit.edu>,
        "'wendell@mit.edu'" <wendell@mit.edu>,
        "'devries@mit.edu'" <devries@mit.edu>,
        "'fulton@psfc.mit.edu'"
	 <fulton@psfc.mit.edu>,
        "'hrycaj@pfc.mit.edu'" <hrycaj@pfc.mit.edu>,
        "'mlej@mit.edu'" <mlej@mit.edu>
Cc: "'rtdavis@mit.edu'" <rtdavis@mit.edu>,
        "'shutdown@plant.mit.edu'"
	 <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Tue, 17 Apr 2001 15:02:39 -0400
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"

A major steam to hot water conversion system that is underway in NW14 
will affect NW12, NW13, NW14, and NW15.  The heating supplied to 
those buildings will come directly from the Institute's central 
utility plant rather than from the old boilers as it does now.  In 
the interim, the heat to those buildings will be supplied from a 
smaller unit than is normally used. The replacement of the heating 
units was scheduled for the warmer weather months so it would not 
inconvenience the community.  It began last week and will continue 
throughout the summer and should be completed by September.

Unfortunately, the below normal temperatures expected for this week 
may result in cooler than normal buildings.  Although we anticipate 
that the buildings will be heated to a temperature of 65 degrees, we 
wanted to make you aware so that may wear suitable clothing.

When completed, the hot water conversion plan will heat most of the 
northwest campus.  The work with the NW buildings is in conjunction 
with the utility construction taking place in the railroad right of 
way.

Any questions on this project may be directed to Roger Moore, 
superintendent of utilities, at ext. 3-2347.