[54660] in Hotline Meeting
Bldg. 9 - 4/21 - Air Handlers 1 and 2 Shutdown Request (Continuat
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Apr 17 08:05:01 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2265@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'deedc@mit.edu'" <deedc@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'jobrien@mit.edu'" <jobrien@MIT.Edu>,
"'kirky@ceci.mit.edu'"
<kirky@ceci.mit.edu>,
"'mlavalle@mitvma.mit.edu'"
<mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'" <ndk@MIT.Edu>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
"'randy@mit.edu'"
<randy@MIT.Edu>,
"'sexton@mit.edu'" <sexton@MIT.Edu>, "'src@mit.edu'"
<src@MIT.Edu>,
"'westlund@mit.edu'" <westlund@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 17 Apr 2001 08:04:55 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; Cust-Coach; deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> kirky@ceci.mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu;
> pam@ceci.mit.edu; randy@mit.edu; sexton@mit.edu; src@mit.edu;
> westlund@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 9 - 4/21 - Air Handlers 1 and 2 Shutdown Request
> (Continuation from 4/7)
>
>
The following Air Handlers 1 and 2 shutdown request for Bldg. 9 (a
continuation from 4/7) on Saturday, 4/21 is for your review and comment.
Would you please let me know whether this does or does not have your
approval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 9
> Date: 4/21/2001
> Day: Saturday
> Time: 7 AM - 7 PM
> System: Air Handlers 1 and 2
> Duration: 12 hours
> Reason:
> Welding at air intakes
>
> Effect:
> Loss of supply ventialtion, supply cooling and supply heating during the