Bldg. 54 - 3rd floor - 4/17 Emergency Electrical Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Apr 13 14:43:09 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD225E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'kvkeefe@mit.edu'" <kvkeefe@MIT.Edu>,
        "'politano@mit.edu'"
	 <politano@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sdl-adm-lib@mit.edu'" <sdl-adm-lib@MIT.Edu>,
        "'w1mx-officers@mit.edu'"
	 <w1mx-officers@MIT.Edu>,
        "'wendell@mit.edu'" <wendell@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
        "'opsnote@mit.edu'"
	 <opsnote@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>, A-Zone <A-Zone@MIT.Edu>
Date: Fri, 13 Apr 2001 14:41:44 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; Cust-Coach; kvkeefe@mit.edu; politano@mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; w1mx-officers@mit.edu;
> wendell@mit.edu; shutdowns@mit.edu; opsnote@mit.edu; schedule@mit.edu;
> mmahoney@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; A-Zone
> Subject: 	Bldg. 54 - 3rd floor - 4/17 Emergency Electrical Shutdown
> 
> 
The following Emergency electricalshutdown for Bldg. 54 - 3rd floor on
Tuesday, 4/17 is for your information.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Emergency
> Building: 54 - 3rd floor
> Date: 4/17/2001
> Day: Tuesday
> Time: 7:30 AM - 1:30 PM
> System: Electrical
> Duration: 6 hours
> Reason: 
> Defective 250 Amp circuit Breaker.
> 
> Effect: 
> Loss of building power, computers, telephones and lighting during the
> 6-hour shutdown period.
> 
> 