Bldg. 39 - 5th Floor - 4/18 - Heating Hot Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Apr 12 13:58:06 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2248@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'mcgrath@mtl.mit.edu'" <mcgrath@mtl.mit.edu>,
"'rcf@space.mit.edu'"
<rcf@space.mit.edu>,
"'walsh@mtl.mit.edu'" <walsh@mtl.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 12 Apr 2001 13:57:58 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; mcgrath@mtl.mit.edu; rcf@space.mit.edu;
> walsh@mtl.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 39 - 5th Floor - 4/18 - Heating Hot Water Shutdown
> Request
>
>
The following heating hot water shutdown request for Bldg. 39 - 5th floor on
Wednesday, 4/18 is for your information and comment. Would you please let
me know whether this does or does not have your approval.
Thanks very much,
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 39 - 5th floor
> Date: 4/18/2001
> Day: Wednesday
> Time: 7 AM - 11 AM
> System: Heating hot water
> Duration: 4 hours
> Reason:
> Installation of new reheat coils in shaftways.
>
> Effect:
> Loss of heating hot water (no reheats on Bldg. 39 - 5th floor) for
> duration of shutdown period.
>
>