Bldg. 9 - Revised Shutdown Date (3/31)

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Mar 29 08:40:20 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD213E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'deedc@mit.edu'" <deedc@MIT.Edu>,
        "'gallant@mit.edu'" <gallant@MIT.Edu>,
        "'jobrien@mit.edu'" <jobrien@MIT.Edu>,
        "'kirky@ceci.mit.edu'"
	 <kirky@ceci.mit.edu>,
        "'mlavalle@mitvma.mit.edu'"
	 <mlavalle@mitvma.mit.edu>,
        "'ndk@mit.edu'" <ndk@MIT.Edu>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
        "'randy@mit.edu'"
	 <randy@MIT.Edu>,
        "'sexton@mit.edu'" <sexton@MIT.Edu>, "'src@mit.edu'"
	 <src@MIT.Edu>,
        "'westlund@mit.edu'" <westlund@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        Warren Scott
	 <WScott@PLANT.MIT.EDU>,
        Joe Vella <jpvella@PLANT.MIT.EDU>
Date: Thu, 29 Mar 2001 08:39:56 -0500
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"

Dear Everyone:

The date for the Air Handlers 1 and 2 for Building 9 is supposed to be
Saturday, 3/31 not Saturday, 4/3 which is obviously incorrect.

Would you please let me know if this new date and correct day meets with
your approval or does not.

Thank you again for your time and we apologize for the incorrect
information.

Andrea Nichols
Operations Center
8-7872

home help back first fref pref prev next nref lref last post