Bldg. 9 - 4/3 - Air Handlers 1 and 2 Critical Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Mar 28 13:59:26 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2137@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'deedc@mit.edu'" <deedc@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'jobrien@mit.edu'" <jobrien@MIT.Edu>,
"'kirky@ceci.mit.edu'"
<kirky@ceci.mit.edu>,
"'mlavalle@mitvma.mit.edu'"
<mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'" <ndk@MIT.Edu>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
"'randy@mit.edu'"
<randy@MIT.Edu>,
"'sexton@mit.edu'" <sexton@MIT.Edu>, "'src@mit.edu'"
<src@MIT.Edu>,
"'westlund@mit.edu'" <westlund@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 28 Mar 2001 13:58:55 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; Cust-Coach; deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> kirky@ceci.mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu;
> pam@ceci.mit.edu; randy@mit.edu; sexton@mit.edu; src@mit.edu;
> westlund@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 9 - 4/3 - Air Handlers 1 and 2 Critical Shutdown
> Request
>
>
The following Critical shutdown request for Bldg. 9 (Air Handlers 1 and 2)
on Saturday, 4/3 is for your review and comment. Would you please let me
know whether this shutdown request has your approval or does not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Critical
> Building: 9
> Date: 4/3/2001
> Day: Saturday
> Time: 7 AM - 7 PM
> System: Air Handlers 1 and 2
> Duration: 12 hours
> Reason:
> Welding at Air Intake.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating during the
> 12 hour shutdown period.
>
>