[54390] in Hotline Meeting
Bldg. N51 - 3/29 PM - 3/30 AM - Electrical Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 27 09:21:12 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD210B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'arhodes@mit.edu'" <arhodes@mit.edu>,
"'cbdewart@mit.edu'"
<cbdewart@mit.edu>, D-Zone <D-Zone@mit.edu>,
"'honda@mit.edu'"
<honda@mit.edu>, "'mleen@mit.edu'" <mleen@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 27 Mar 2001 09:20:46 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: arhodes@mit.edu; cbdewart@mit.edu; D-Zone; honda@mit.edu;
> mleen@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. N51 - 3/29 PM - 3/30 AM - Electrical Power Shutdown
> Request
>
>
The following electrical power shutdown request for Bldg. N51 on Thursday,
3/29 PM to Friday, 3/30 AM is for your review and comment. Would you please
let me know whether this does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: N51
> Date: 3/29/2001
> Day: Thursday
> Time: 3/29 (11 PM) - 3/30 (7 AM)
> System: Electrical Power
> Duration: 8 hours
> Reason:
> Transfer of power to new lines from temporary lines.
>
> Effect:
> Loss of electric power: Access controls, building power, elevators,
> lighting/corridors-stairs; Air: Supply ventilation and exhaust-general
> air during the shutdown period.
>
>