[54256] in Hotline Meeting

home help back first fref pref prev next nref lref last post

W7 and Theta Delta Chi - 3/20 - All Building Normal Power Shutdow

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Mar 16 12:05:58 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD204B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'kcn@mit.edu'" <kcn@mit.edu>, "'gscot@mit.edu'" <gscot@mit.edu>,
        "'dvallay@mit.edu'" <dvallay@mit.edu>,
        "'jnolan@mit.edu'"
	 <jnolan@mit.edu>,
        "'mwhelan@mit.edu'" <mwhelan@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 16 Mar 2001 12:05:51 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	kcn@mit.edu; gscot@mit.edu; dvallay@mit.edu; jnolan@mit.edu;
> mwhelan@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	W7 and Theta Delta Chi - 3/20 - All Building Normal Power
> Shutdown Reuqest
> 
> 
The following all building normal power shutdown request for W7 (Baker
House) and Theta Delta Chi (at 372 Memorial Drive) on Tuesday, 3/20 is for
your review and  comment.  Would you please let me know whether this does or
does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: W7 (Baker House) and Theta Delta Chi
> Date: 3/20/2001
> Day: Tuesday
> Time: 10:30 AM - 11:30 AM 
> System: All building normal power 
> Duration: 20 minutes within the above-listed time frame
> Reason: 
> Determine phasing for future shutdowns in W61.
> 
> Effect: 
> Loss of Power:  access controls, building power, computers and lighting.
> 
> 

home help back first fref pref prev next nref lref last post