Building 8 and 6- 3/20 - Hot and Cold Domestic and Lab Process Wa
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 13 11:16:11 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD2008@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'carolr@mit.edu'" <carolr@mit.edu>, Cust-Coach <cust-coach@mit.edu>,
"'cwyckoff@mit.edu'" <cwyckoff@mit.edu>,
"'glabonte@mit.edu'"
<glabonte@mit.edu>,
"'kmartel@mit.edu'" <kmartel@mit.edu>,
"'lechtman@mit.edu'" <lechtman@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>, C-Zone
<C-Zone@mit.edu>,
"'doreenc@mit.edu'" <doreenc@mit.edu>,
"'khewitt@mit.edu'" <khewitt@mit.edu>, "'mbj@mit.edu'" <mbj@mit.edu>,
"'mhankin@mit.edu'" <mhankin@mit.edu>,
"'naylor@mit.edu'"
<naylor@mit.edu>,
"'rjwilk@mit.edu'" <rjwilk@mit.edu>,
"'rrdasari@mit.edu'" <rrdasari@mit.edu>,
"'saraf@mit.edu'"
<saraf@mit.edu>, "'tiki@mit.edu'" <tiki@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 13 Mar 2001 11:16:04 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: carolr@mit.edu; Cust-Coach; cwyckoff@mit.edu; glabonte@mit.edu;
> kmartel@mit.edu; lechtman@mit.edu; schedule@mit.edu; shutdowns@mit.edu;
> C-Zone; doreenc@mit.edu; khewitt@mit.edu; mbj@mit.edu; mhankin@mit.edu;
> naylor@mit.edu; rjwilk@mit.edu; rrdasari@mit.edu; saraf@mit.edu;
> tiki@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Building 8 and 6- 3/20 - Hot and Cold Domestic and Lab
> Process Water Shutdown Request
>
>
The following hot and cold domestic and lab process water shutdown request
for Bldg. 8 and hot domestic/lab process water for Bldg. 6 on Tuesday, 7/20
is for your review and comment. Would you please let me know whether this
does or does not meet with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 8 and 6
> Date: 3/20/2001
> Day: Tuesday
> Time: 7 AM - 11 AM
> System: Hot and cold domestic and lab process water
> Duration: 4 hours
> Reason:
> Tie in new water line.
>
> Effect:
> Loss of hot and cold domestic water (bathroom, kitchen sink faucets and
> drinking fountains) as well as hot and cold lab process water sink faucets
> in Bldg. 8. The toilets will still be working during the 4-hour shutdown
> period. There will be no hot domestic or lab process water in Building 6
> during the shutdown period.
>
>