Bldg. 36 - 3/8 - Approved Emergency Electrical Panel Shutdown Req

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Mar 7 15:25:35 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451BD1FCA@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@mit.edu>,
        "'cperry@mit.edu'"
	 <cperry@mit.edu>,
        "'pbaratta@mit.edu'" <pbaratta@mit.edu>,
        "'mmahoney@mit.edu'" <mmahoney@mit.edu>,
        David Ferrante
	 <dferrant@PLANT.MIT.EDU>,
        Howard  Harrison <HHarriso@PLANT.MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'lambert@mitvma.mit.edu'"
	 <lambert@mitvma.mit.edu>,
        "'ladd@tower.lsc.mit.edu'"
	 <ladd@tower.lsc.mit.edu>,
        "'natkin@hq.mit.edu'" <natkin@hq.mit.edu>,
        "'jmganno@mit.edu'" <jmganno@mit.edu>,
        "'lukeohane@mit.edu'"
	 <lukeohane@mit.edu>,
        "'tdalton@mit.edu'" <tdalton@mit.edu>,
        John Denucce
	 <jdenucce@PLANT.MIT.EDU>,
        "'mcgrath@mtl.mit.edu'" <mcgrath@mtl.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Wed, 7 Mar 2001 15:25:21 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	dcarlson@mit.edu; cperry@mit.edu; pbaratta@mit.edu;
> mmahoney@mit.edu; David Ferrante; Howard  Harrison; shutdowns@mit.edu;
> lambert@mitvma.mit.edu; ladd@tower.lsc.mit.edu; natkin@hq.mit.edu;
> jmganno@mit.edu; lukeohane@mit.edu; tdalton@mit.edu; John Denucce;
> mcgrath@mtl.mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: 	Bldg. 36 - 3/8 - Approved Emergency Electrical Panel
> Shutdown Request
> 
> 
The following approved emergency power shutdown for Bldg. 36 which will also
affect buildings 34 and 39 for FCS is for your information.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 36
> Date: 3/8/2001
> Day: Thursday
> Time: 7:30 AM - 4:00 PM
> System: Emergency Power
> Duration: 8 1/2 hours
> Reason: 
> Add more room to the panel for the elevator recall of the Fire Alarm
> System.
> 
> Effect: 
> Loss of emergency power in Bldg. 36. This means no exit lights or air
> dryers will be operational.  This will also affect  FCS alarm monitoring
> for Buildings 34, 36 and 39 during the shutdown period.
> 
> 