[54116] in Hotline Meeting
Bldg. 36 - 3/8 - Approved Emergency Electrical Panel Shutdown Req
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Mar 7 15:25:35 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD1FCA@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@mit.edu>,
"'cperry@mit.edu'"
<cperry@mit.edu>,
"'pbaratta@mit.edu'" <pbaratta@mit.edu>,
"'mmahoney@mit.edu'" <mmahoney@mit.edu>,
David Ferrante
<dferrant@PLANT.MIT.EDU>,
Howard Harrison <HHarriso@PLANT.MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'lambert@mitvma.mit.edu'"
<lambert@mitvma.mit.edu>,
"'ladd@tower.lsc.mit.edu'"
<ladd@tower.lsc.mit.edu>,
"'natkin@hq.mit.edu'" <natkin@hq.mit.edu>,
"'jmganno@mit.edu'" <jmganno@mit.edu>,
"'lukeohane@mit.edu'"
<lukeohane@mit.edu>,
"'tdalton@mit.edu'" <tdalton@mit.edu>,
John Denucce
<jdenucce@PLANT.MIT.EDU>,
"'mcgrath@mtl.mit.edu'" <mcgrath@mtl.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Wed, 7 Mar 2001 15:25:21 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: dcarlson@mit.edu; cperry@mit.edu; pbaratta@mit.edu;
> mmahoney@mit.edu; David Ferrante; Howard Harrison; shutdowns@mit.edu;
> lambert@mitvma.mit.edu; ladd@tower.lsc.mit.edu; natkin@hq.mit.edu;
> jmganno@mit.edu; lukeohane@mit.edu; tdalton@mit.edu; John Denucce;
> mcgrath@mtl.mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. 36 - 3/8 - Approved Emergency Electrical Panel
> Shutdown Request
>
>
The following approved emergency power shutdown for Bldg. 36 which will also
affect buildings 34 and 39 for FCS is for your information.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 36
> Date: 3/8/2001
> Day: Thursday
> Time: 7:30 AM - 4:00 PM
> System: Emergency Power
> Duration: 8 1/2 hours
> Reason:
> Add more room to the panel for the elevator recall of the Fire Alarm
> System.
>
> Effect:
> Loss of emergency power in Bldg. 36. This means no exit lights or air
> dryers will be operational. This will also affect FCS alarm monitoring
> for Buildings 34, 36 and 39 during the shutdown period.
>
>