Shutdown request for building E18 and E19 on 3/7

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Mar 5 12:20:20 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451FB8F65@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: AUFIERO@MIT.EDU, bengel@MIT.EDU, dudley@MIT.EDU, E-Zone
	 <E-Zone@MIT.EDU>,
        jmganno@MIT.EDU, lombardo@MIT.EDU, lstcroix@MIT.EDU, nsteele@MIT.EDU,
        safety@MIT.EDU, shyoung@MIT.EDU, bengel@MIT.EDU, cschultz@MIT.EDU,
        dcairns@MIT.EDU, dlking@MIT.EDU, dshea@MIT.EDU, dturn@MIT.EDU,
        E-Zone <E-Zone@MIT.EDU>, e19site@MIT.EDU, elsagt@MIT.EDU,
        esico@MIT.EDU, hallisey@MIT.EDU, honiker@MIT.EDU, joconor@MIT.EDU,
        kelley@MIT.EDU, kshooter@MIT.EDU, lambert@mitvma.mit.edu, lkn@MIT.EDU,
        mbowers@MIT.EDU, Mary Tobin <mtobin@PLANT.MIT.EDU>, narbonne@MIT.EDU,
        opsnote@MIT.EDU, rberlin@MIT.EDU, rrhonda@MIT.EDU, safety@MIT.EDU,
        sfalconi@MIT.EDU, Steve Miscowski <SMiscows@PLANT.MIT.EDU>,
        tdalton@MIT.EDU, tmeehan@MIT.EDU, wbarrett@MIT.EDU, shutdowns@MIT.EDU,
        schedule@MIT.EDU
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 5 Mar 2001 12:20:09 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	AUFIERO@MIT.EDU; bengel@mit.edu; dudley@mit.edu; E-Zone;
> jmganno@mit.edu; lombardo@mit.edu; lstcroix@mit.edu; nsteele@mit.edu;
> safety@mit.edu; shyoung@mit.edu; bengel@mit.edu; cschultz@mit.edu;
> dcairns@mit.edu; dlking@mit.edu; dshea@mit.edu; dturn@mit.edu; E-Zone;
> e19site@mit.edu; elsagt@mit.edu; esico@mit.edu; hallisey@mit.edu;
> honiker@mit.edu; joconor@mit.edu; kelley@mit.edu; kshooter@mit.edu;
> lambert@mitvma.mit.edu; lkn@mit.edu; mbowers@mit.edu; Mary Tobin;
> narbonne@MIT.EDU; opsnote@mit.edu; rberlin@mit.edu; rrhonda@mit.edu;
> safety@mit.edu; sfalconi@mit.edu; Steve Miscowski; tdalton@mit.edu;
> tmeehan@mit.edu; wbarrett@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building E18 and E19 on 3/7
> 
> 
The following shutdown request is for building E19 and E18 on 3/7.  Please
let me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: E18 and E19
> Date: 3/7/01
> Day: Wednesday
> Time: 7 am - 3 pm
> System: Fire protection water
> Duration: 8 hours
> Reason: 
> Rework sprinkler heads in E19 and E18.
> 
> Effect: 
> The fire protection water will be down during this time.
> 
> 