Emergency shutdown for building 8 on 2/28
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Feb 27 09:36:02 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451FB8A15@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: Warren Scott <WScott@PLANT.MIT.EDU>, C-Zone <C-Zone@MIT.Edu>,
carolr@MIT.Edu, Cust-Coach <cust-coach@MIT.Edu>, cwyckoff@MIT.Edu,
glabonte@MIT.Edu, kmartel@MIT.Edu, lechtman@MIT.Edu, schedule@MIT.Edu,
shutdowns@MIT.Edu, Operators <Operators@PLANT.MIT.EDU>,
dcarlson@MIT.Edu, cperry@MIT.Edu, pbaratta@MIT.Edu, mmahoney@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 27 Feb 2001 09:35:54 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: Warren Scott; C-Zone; carolr@mit.edu; Cust-Coach; cwyckoff@mit.edu;
> glabonte@mit.edu; kmartel@mit.edu; lechtman@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; Operators; dcarlson@mit.edu; cperry@mit.edu;
> pbaratta@mit.edu; mmahoney@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Emergency shutdown for building 8 on 2/28
>
>
The following emergency shutdown for building 8 on 2/28 is for your
information.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Emergency
> Building: 8
> Date: 2/28/01
> Day: Wednesday
> Time: 7 am - 9 am
> System: Domestic and lab processed hot water.
> Duration: 2 hours
> Reason:
> Replace a broken valve on a hot water tank.
>
> Effect:
> There will be a loss of hot domestic and lab processed water during this
> time.
>
>