[54010] in Hotline Meeting
Shutdown request for building E25 on 3/2
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Feb 26 09:01:55 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451EE955C@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: andrea@psyche.mit.edu, arolle@mit.edu, bengel@mit.edu, cpoon@mit.edu,
E-Zone <E-Zone@mit.edu>, elworthi@mit.edu, hegarty@mit.edu,
jmganno@mit.edu, jrauch@mit.edu, loudib@mit.edu, rfink@mit.edu,
roge@med.mit.edu, schedule@mit.edu, sdl-adm-lib@mit.edu,
shyoung@mit.edu, shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 26 Feb 2001 09:01:47 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: andrea@psyche.mit.edu; arolle@mit.edu; bengel@mit.edu;
> cpoon@mit.edu; E-Zone; elworthi@mit.edu; hegarty@mit.edu; jmganno@mit.edu;
> jrauch@mit.edu; loudib@mit.edu; rfink@mit.edu; roge@med.mit.edu;
> schedule@mit.edu; sdl-adm-lib@mit.edu; shyoung@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building E25 on 3/2
>
>
The following shutdown request is for building E25 on 3/2. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: E25
> Date: 3/2/01
> Day: Friday
> Time: 7:30 am - 11:30 am
> System: Smoke detectors
> Duration: 4 hours
> Reason:
> Welding of valve on air handler 4 condensate.
>
> Effect:
> The smoke detectors will be down during this time.
>
>