Shutdown request for building W13 on 2/28

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Feb 23 13:10:35 2001

Message-Id: <82F0D564C5ADD31180EF00508B556451EE94BA@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.EDU>, kcn@MIT.EDU, mwhelan@MIT.EDU, schedule@MIT.EDU,
        shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 23 Feb 2001 13:10:26 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	D-Zone; kcn@mit.edu; mwhelan@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building W13 on 2/28
> 
> 
The following shutdown request is for building W13 on 2/28.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: W13 
> Date: 2/28/01
> Day: Wednesday
> Time: 7:30am  - 3:30 pm
> System: Fire alarms and heat detectors
> Duration: 8 hours
> Reason: 
> To relocate hest detectors in kitchen in section 46.
> 
> Effect: 
> The fire alarms will be down during this time.
> 
> 