Shutdown request for building E52 on 2/27

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Feb 21 11:59:51 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451EE9289@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.Edu>, gwj@MIT.Edu, lhill@MIT.Edu, lmorales@MIT.Edu,
        lreinher@MIT.Edu, maureen@MIT.Edu, mscoppa@MIT.Edu, mwf@MIT.Edu,
        rberlin@MIT.Edu, schedule@MIT.Edu, sdimond@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 21 Feb 2001 11:59:40 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	E-Zone; gwj@mit.edu; lhill@mit.edu; lmorales@mit.edu;
> lreinher@mit.edu; maureen@mit.edu; mscoppa@mit.edu; mwf@mit.edu;
> rberlin@mit.edu; schedule@mit.edu; sdimond@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building E52 on 2/27
> 
> 
The following shutdown request is for building E52 on 2/27/01.  Please let
me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: E52
> Date: 2/27/01
> Day: Tuesday
> Time: 7:30 am - 10:30 am
> System: Supply fans 3 (PM#700026) and 5 (PM#700028)
> Duration: 1 1/2 hours each
> Reason: 
> Bag filter changes.
> 
> Effect: 
> There will be a loss of supply air ventilation, supply air cooling and
> supply air heating for each supply fan while it is down.  Supply fan 3
> will effect the center bay areas and supply fan 5 will affect west area.
> 
> 