[53870] in Hotline Meeting
Shutdown request for building 39 on 2/26
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Feb 15 09:41:43 2001
Message-Id: <82F0D564C5ADD31180EF00508B556451EE8F0E@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
mcgrath@mtl.mit.edu, rcf@space.mit.edu, walsh@mtl.mit.edu,
schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 15 Feb 2001 09:41:34 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; mcgrath@mtl.mit.edu; rcf@space.mit.edu;
> walsh@mtl.mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 39 on 2/26
>
>
The following shutdown request is for building 39 on 2/26/01. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 39
> Date: 2/26/01
> Day: Monday
> Time: 7 am - 9 am
> System: Labortory vacuum
> Duration: 2 hours
> Reason:
> Maintenance inspection (change filters, oil, etc.)
>
> Effect:
> The lab vacuum will be down during this time.
>
>