[53272] in Hotline Meeting
NW61 Shutdown request for 1/5/01
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Dec 28 13:15:44 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451D2B938@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, kcn@MIT.Edu, mwhelan@MIT.Edu, schedule@MIT.Edu,
shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 28 Dec 2000 13:15:37 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: D-Zone; kcn@mit.edu; mwhelan@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: NW61 Shutdown request for 1/5/01
>
>
The following shutdown for NW61 is scheduled for 1/5/01. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: NW61
> Date: 1/5/01
> Day: Friday
> Time: 7 am - 3 pm
> System: Sprinkler
> Duration: 8 hours
> Reason:
> Install replacement sprinkler heads in the basements
>
> Effect:
> Fire protection water.
>
>