[53257] in Hotline Meeting
Building 18 shutdown request rescheduled for 12/29
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Dec 27 11:23:36 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451D2B861@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, akelsey@MIT.Edu,
Cust-Coach
<cust-coach@MIT.Edu>, mbj@MIT.Edu, rjwilk@MIT.Edu,
scheudle@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 27 Dec 2000 11:23:21 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; akelsey@mit.edu; Cust-Coach; mbj@mit.edu; rjwilk@mit.edu;
> scheudle@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Building 18 shutdown request rescheduled for 12/29
>
>
The following shutdown request is for building 18 on 12/29. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 18
> Date: 12/29/00
> Day: Friday
> Time: 6:30 am - 10:30
> System: All plumbing services
> Duration: 4 hours
> Reason:
> To cut and cap shaft #1 and refeed services to magnetic lab (sub-basement)
> and laser lab (basement)
>
> Effect:
> There will be a loss of hot and cold lab processed water. Hot and cold
> domestic water. Compressed air and lab vacuum air. Also natural gas.
>
>