Building 39 shtudown request rescheduled for 1-6-01

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Dec 27 07:59:12 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451D2B7FC@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.EDU>, Cust-Coach <cust-coach@MIT.EDU>,
        mcgrath@mtl.mit.edu, rcf@space.mit.edu, walsh@mtl.mit.edu,
        schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Wed, 27 Dec 2000 07:59:01 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; mcgrath@mtl.mit.edu; rcf@space.mit.edu;
> walsh@mtl.mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Building 39 shtudown request rescheduled for 1-6-01
> 
> 
The following shutdown for building 39 is being rescheduled to 1-6-01.
Please let me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599 

> Status: Critical
> Building: 39
> Date: 1/6/01
> Day: Saturday
> Time: 8 am - 4 pm
> System: AH1, AH2, AH3, & AH4
> Duration: 8 Hours
> Reason: 
> Box filter changes.
> 
> Effect: 
> There will be a loss of supply air ventilation, supply cooling air and
> supply heating air.     The air handlers will not go down all at the same
> time.  They will only have one down at a time.
> 
> 