[53223] in Hotline Meeting
Shutdown request for building 18 on 12/27
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Dec 21 12:40:27 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451D2B671@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, akelsey@MIT.EDU,
Cust-Coach
<cust-coach@MIT.EDU>, mbj@MIT.EDU, rjwilk@MIT.EDU,
schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 21 Dec 2000 12:40:18 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: A-Zone; akelsey@mit.edu; Cust-Coach; mbj@mit.edu; rjwilk@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 18 on 12/27
>
>
The following shutdown request is for building 18 on 12/27. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
2-1599
> Status: Normal
> Building: 18 Entire building
> Date: 12/27/00
> Day: Wednesday
> Time: 7:30 am - 2:30 pm
> System: All plumbing service
> Duration: 7 hours
> Reason:
> To cut and cap shaft #1 and refeed services to magnetic lab (sub-basement)
> and laser lab (basement)
>
> Effect:
> There will be a loss of hot and cold lab processed water. Hot and cold
> domestic water. Compressed air and lab vacuum air. Also natural gas.
>
>