Shutdown request for building 18 on 12/27

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Dec 21 12:40:27 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451D2B671@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, akelsey@MIT.EDU,
        Cust-Coach
	 <cust-coach@MIT.EDU>, mbj@MIT.EDU, rjwilk@MIT.EDU,
        schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 21 Dec 2000 12:40:18 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; akelsey@mit.edu; Cust-Coach; mbj@mit.edu; rjwilk@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building 18 on 12/27
> 
> 
The following shutdown request is for building 18 on 12/27.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
2-1599

> Status: Normal
> Building: 18 Entire building 
> Date: 12/27/00
> Day: Wednesday
> Time: 7:30 am - 2:30 pm 
> System: All plumbing service
> Duration: 7 hours
> Reason: 
> To cut and cap shaft #1 and refeed services to magnetic lab (sub-basement)
> and laser lab (basement)
> 
> Effect: 
> There will be a loss of hot and cold lab processed water.  Hot and cold
> domestic water.  Compressed air and lab vacuum air.  Also natural gas.
> 
> 